Legislation Details

File #: 24-1008    Version: 2 Name:
Type: Regular Item Status: Adopted
File created: 6/26/2024 In control: Board of Supervisors
On agenda: 7/23/2024 Final action: 7/23/2024
Title: JAIL RE-ENTRY FACILITY PROJECT - Administrative Services Director Tom Provine
Indexes: Jail Re-Entry Project
Attachments: 1. Change Order 3.pdf, 2. Change Order 2.pdf

title

JAIL RE-ENTRY FACILITY PROJECT - Administrative Services Director Tom Provine

end

 

Requested Action(s)

recommendation

a)                     CHANGE ORDER - Request confirmation of Change Order No. 2 to the agreement with D.H. Slater & Son, Inc. (Misc. Agree. #2023-298) for the Tehama County Re-Entry Facility, thereby allowing for changes as listed, for a contract increase in the amount of $69,245.60

 

b)                     CHANGE ORDER - Request confirmation of Change Order No. 3 to the agreement with D.H. Slater & Son, Inc. (Misc. Agree. #2023-298) for the Tehama County Re-Entry Facility, thereby allowing for changes as listed, for a contract decrease in the amount of $37,099.55

body

 

Financial Impact:

The cost of these change orders is included in the project budget

 

Background Information:

Construction of the Jail Re-Entry Facility began in December. As work has progressed, minor changes have been necessary in the course of the project. Change Orders 2 and 3 include responses to unanticipated conditions and changes determined to be in the County’s best interest, including some that provided significant savings. Details of the changes are included in the attached change order forms.

 

The net change of these items is an increase in overall cost of $32,146.15, with a total change order increase for the project of $31,388.23. The total of change order costs to date is 3% of the Board-authorized change order authority, and nothing is outside the range of ordinary change orders or outside the project budget’s contingency.