Legislation Details

File #: 25-0715    Version: 1 Name:
Type: Regular Item Status: Adopted
File created: 4/23/2025 In control: Board of Supervisors
On agenda: 5/13/2025 Final action: 5/13/2025
Title: PUBLIC WORKS - Interim Director Will Pike
Attachments: 1. Evergreen CCO #13 Supplemental #1.pdf, 2. Evergreen CCO #13 Supplemental #1 Memo.pdf, 3. Evergreen CCO #23.pdf, 4. Evergreen CCO#23 Memo.pdf, 5. Evergreen CCO #26.pdf, 6. Evergreen CCO#26 Memo.pdf, 7. Evergreen CCO #29.pdf, 8. Evergreen CCO#29 Memo.pdf, 9. Evergreen CCO #30.pdf, 10. Evergreen CCO#30 Memo.pdf, 11. Evergreen CCO #31.pdf, 12. Evergreen CCO#31 Memo.pdf, 13. Evergreen CCO #34.pdf, 14. Evergreen CCO#34 Memo.pdf
title
PUBLIC WORKS - Interim Director Will Pike
end

Requested Action(s)
recommendation
a) CHANGE ORDER - Request authorization for the Interim Director to issue Change Order No. 13 Supplement No. 1, to Agreement with JF Shea Inc. (Road Agreement #2022-23) for the Evergreen Road Bridge Replacement Project, for the extended rental and removal cost of the sheet piling used to divert groundwater, in an amount equal to $154,010.04

b) CHANGE ORDER - Request authorization for the Interim Director to issue Change Order No. 23, to the Agreement with JF Shea Inc. (Road Agreement #2022-23) for the Evergreen Road Bridge Replacement Project, to modify inlet elevations at Drainage System 1 locations (e) and (g), in an amount equal to $7,170

c) CHANGE ORDER - Request authorization for the Interim Director to issue Change Order No. 26, to the Agreement with JF Shea Inc. (Road Agreement #2022-23) for the Evergreen Road Bridge Replacement Project, to realign Ditch "D2", in an amount equal to $23,008.86

d) CHANGE ORDER - Request authorization for the Interim Director to issue Change Order No. 29, to the Agreement with JF Shea Inc. (Road Agreement #2022-23) for the Evergreen Road Bridge Replacement Project, to change the Type 85 bridge rail barrier post spacing from 10'-0" to 6'-7", in an amount equal to $27,317.85

e) CHANGE ORDER - Request authorization for the Interim Director to issue Change Order No. 30, to the Agreement with JF Shea Inc. (Road Agreement #2022-23) for the Evergreen Road Bridge Replacement Project, to install drainage culverts at Driveway 3, Driveway 4, and modify Ditch "D14", in an amount equal to $22,092.09

f) CHANGE ORDER - Request authorization for the Interim Director to issue Change Order No. 31, to the Agreement with JF Shea Inc. (Road Agreement #2022-23) for the Evergreen Road Bridge Replacement Project, to install corrugated steel pipe (CSP) down drains in lieu of hot mix asphalt (HMA) overside drains, in an amount equal to $2,821.33

g) CHANGE ...

Click here for full text