title
PUBLIC WORKS - Director Jim Simon
end
Requested Action(s)
recommendation
a) ROAD AGREEMENT - Request approval and authorization for the Director to sign Amendment #2 to the Agreement with Consor Engineering (formerly Quincy Engineering), (Road Agree. # 2019-19 amended by #2022-3) for the purpose of providing construction management services related to the Jellys Ferry Road at Sacramento River Bridge Replacement Project; thereby extending the Performance Period from five (5) years to six (6) years
body
Financial Impact:
This amendment does not affect funding.
Background Information:
The Board awarded a contract for construction management services for the Jellys Ferry Road at Sacramento River Bridge Replacement Project to Quincy Engineering at its November 19, 2019, meeting. The Board approved Amendment No. 1 to increase the contract amount at its March 7, 2022, meeting.
Additional time is required to complete final project documentation and environmental monitoring.