Title: PUBLIC WORKS - Public Works Director Jim Simon
Attachments: 1. CCO-1.pdf, 2. CCO-4.pdf, 3. CCO-6.pdf, 4. CCO-8.pdf, 5. CCO-10.pdf, 6. CCO-17.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

PUBLIC WORKS - Public Works Director Jim Simon

end

 

Requested Action(s)

recommendation

a) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 1 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform monthly water quality testing, in an amount equal to $7,590

 

b) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 4 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform potholing, in an amount equal to $15,000

 

c) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 6 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform potholing, in an amount equal to $11,778.01

 

d) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 8 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to remove existing concrete foundations, in an amount equal to $5,000

 

e) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 10 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to maintain existing irrigation systems, in an amount equal to $10,000

 

f) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 17 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to replace sanitary sewer manhole cone section, in an amount equal to $5,000

body

 

Financial Impact:

The total financial impact of CCO No. 1, CCO No. 4, CCO No. 6, CCO No. 8, CCO No. 10 and CCO No. 17 is $54,368.01. The Construction (CON) phase of this project is funded by a combination of Federal and State funds comprised of CMAQ, DEMO, SHOPP, STIP, HIP and RSTP. This project contract is budgeted in Road Fund - Professional and Special Services #3011-53230. The Board awarded the contract for the 99W & South Main Street Project, Federal Project No. RRSTPL 5908(100), County Project No 2708181 to S.T. Rhoads Inc. as the low responsive bidder in the amount of $14,499,406.50 on March 26, 2024 (Road Agreement #2024-03). A 15% contingency, in the amount of $2,213,743.50 was budgeted to the construction contract to address Contract Change Orders and is reimbursable through the project funding. At that time, the Director of Public Works was authorized $210,000 in signature authority for the issuance of Change Orders to the contract, pursuant to Public Contract Code 20405(d)(3).

 

Approval of these Change Orders would leave a remaining contingency budget of $1,472,048.30.

 

Background Information:

The plans call for South Main Street to be reconstructed; however, these changes are necessary to address various field conditions and other contract changes that are beneficial to the project.