Title: Revised FY 2026/2027 Tipping Fee
Attachments: 1. FY 2627 Tipping Fees 10012026
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Revised FY 2026/2027 Tipping Fee

end

 

Requested Action(s)

recommendation

Review and approve the Revised FY 2026/2027 Tipping Fee, as presented.

body

 

Financial Impact:

 

 

Background Information:

When calculating the tipping fee for FY 2026/27, Waste Connections did not account for the reduction in the JPA fee for FY 2026/27. As such, the current tipping fee will need to be lowered. Additionally, Waste Connections will provide the Board with an update on how the excess fees will be refunded to customers.

 

Based upon the above information, staff is requesting approval to adjust the tipping fee as outlined below:

 

 

Approved FY 2026/27

Revised FY 2026/27

Contractor Tip Fee

$111.44

$110.09

Cell Liner Tip Fee

$11.79

$11.79

Phase III Permitting

$0.50

$0.50

Change in Law

$0.00

$0.00

JPA Fee

$0.00

$0.00

Closure Fund

$0.00

$0.00

Total (per ton)

$123.73

$122.38

Minimum Fee (320 pounds)

$19.79

$19.53

 

Once the Board approves the revised tip fee adjustments, Waste Connections will advertise the fees. The revised tipping fee will become effective on October 1, 2026.