Banner image

File #: 24-1686    Version: 1 Name:
Type: Presentation - Comm Status: Agenda Ready
File created: 9/26/2024 In control: Social Services Transportation Advisory Council (SSTAC)
On agenda: 10/3/2024 Final action:
Title: TRAX Facility Presentation - Associate Planner Fox
Attachments: 1. Remodel Completion.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

TRAX Facility Presentation - Associate Planner Fox

end

 

Requested Action(s)

recommendation

Informational presentation on the transit facility remodel and new construction.

body

 

Financial Impact:

None

 

Background Information:

 

The TRAX Bus Maintenance and Administrative Facility Rehabilitation Project, funded with $3 million set aside since 2020, has now been completed. The Tehama County Board awarded a $2 million contract to McCuen Construction Inc. on March 28, 2023, for the base project, with the Director of Public Works authorized an additional $200,000 for change orders.

 

The project faced numerous unknown site conditions due to the lack of available as-built drawings, leading to a substantial list of change orders. The budget for contingencies, including change orders, was set at $1 million, supported by state and federal grants.

 

Over the course of the project, 79 change orders were approved, totaling $1,120,516.58, primarily due to unforeseen conditions. Competitive bidding was bypassed, as it was determined to be impractical and not in the public’s best interest. McCuen Construction, already on-site and familiar with the project, was retained to handle the changes, avoiding costly delays and ensuring efficient project completion.

 

In total, $134,490.73 remains in the contingency budget, with the project successfully completed without exceeding its original financial plan. Associate Planner Fox will present a brief slideshow of the final facility as part of the project’s conclusion.