Skip to main content

Banner image

File #: 25-0157    Version: 1 Name:
Type: Regular Item - Comm Status: Agenda Ready
File created: 1/30/2025 In control: Social Services Transportation Advisory Council (SSTAC)
On agenda: 4/3/2025 Final action:
Title: Swiftly Implementation Project: Deployment for TCTAB - Senior Transportation Planner Fox
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Swiftly Implementation Project: Deployment for TCTAB - Senior Transportation Planner Fox
end

Requested Action(s)
recommendation

Informational Presentation Regarding Automation Applications for TRAX by Senior Transportation Planner Ashley Fox.

body

Financial Impact:

None

Background Information:

Swiftly Implementation Project: Deployment for TRAX

The Swiftly implementation project for the Tehama County Transit Agency Board (TCTAB) was completed, delivering a modernized, real-time transit management system that enhanced operational efficiency and improved passenger experience.

This multi-phase project integrated tracking, data management, and communication tools into TCTAB's TRAX transit operations.

Project Execution & Key Achievements:

Project Coordination & Management
* Swiftly's Implementation Manager, Solutions Architect, and Customer Success Manager collaborated with TCTAB staff to ensure smooth execution.
* TCTAB's Project Sponsor and IT Support Representative facilitated internal
coordination to ensure agency-wide alignment.

Major Implementation Milestones:

Phase 1: Project Kickoff & Technical Scoping
* Stakeholders were aligned, goals were set, and responsibilities were defined.
* A structured project timeline was established, ensuring accountability at every stage.

Phase 2: Data Integration
* TCTAB's GTFS static files were successfully integrated, enabling real-time route and schedule tracking.

Phase 3: Site Survey & Installation Planning
* A virtual fleet assessment was conducted, documenting installation needs and finalizing the Installation Design Document (IDD).

Phase 4: Hardware Procurement & Delivery
* All necessary onboard hardware, including tablets and tracking devices, was procured, configured, and delivered to TCTAB.

Phase 5: Hardware Installation
* All transit vehicles were equipped with real-time tracking devices, ensuring seamless GPS-based monitoring.

Phase 6: Onboard App Software Deployment & Training
* ...