WALNUT STREET COMPLEX SITE ACCESSIBILITY PROJECT

end

 

Requested Action(s)

recommendation

a)                     NOTICE OF COMPLETION - Request approval for the Chair to sign the Notice of

Completion for the Walnut Street Complex Site Accessibility Project, as contracted by

SnL Construction

body

Financial Impact:

This project was fully funded by the Community Development Block Grant (CDBG) program.

 

Background Information:

This project consisted of pavement and sidewalk repairs of an existing parking lot, site ADA upgrades, and additional parking lot striping to match the existing parking lot per specifications. These upgrades and improvements were necessary to protect employees, public and financial investments and County assets.

 

The Board awarded this bid on March 18, 2025, and the project was completed as of November 18, 2025.