title
ADMINISTRATION - Administrative Services Director Tom Provine
end

Requested Action(s)
recommendation
a) CHANGE ORDER - Request confirmation of Change Order No. 4 to the agreement with D.H. Slater & Son, Inc. (Misc. Agree. #2023-298) for the Tehama County Re-Entry Facility, thereby allowing for changes as listed, for a contract increase in the amount of $12,720.65

b) CHANGE ORDER - Request confirmation of Change Order No. 5 to the agreement with D.H. Slater & Son, Inc. (Misc. Agree. #2023-298) for the Tehama County Re-Entry Facility, thereby allowing for changes as listed, for a contract increase in the amount of $29,532.56

c) CHANGE ORDER - Request confirmation of Change Order No. 6 to the agreement with D.H. Slater & Son, Inc. (Misc. Agree. #2023-298) for the Tehama County Re-Entry Facility, thereby allowing for changes as listed, for a contract increase in the amount of $95,507.53

d) CHANGE ORDER - Request confirmation of Change Order No. 7 to the agreement with D.H. Slater & Son, Inc. (Misc. Agree. #2023-298) for the Tehama County Re-Entry Facility, thereby allowing for changes as listed, for a contract increase in the amount of $466,386.20
body

Financial Impact:
The cost of these change orders is included in the project budget.

Background Information:
Construction of the Jail Re-Entry Facility began in December 2024; during the course of the construction project and as work has progressed, several scope adjustments have been identified to address field conditions, coordinate with existing utilities/systems, and maintain progress in critical areas of the project. These adjustments require formal Change Orders to document the revised work scope. The change orders are as follows:

- Change Orders 4 and 5 - Add drainage work, electrical work for the south gate, additional shoring capacity kitchen curbs, adding TV mounts to dayrooms, and other minor changes.

- Change Order 6 - Modifications to laundry venting reconfiguration, lighting fixture m...