Banner image

File #: 24-1854    Version: 1 Name:
Type: Regular Item Status: Agenda Ready
File created: 10/16/2024 In control: Board of Supervisors
On agenda: 11/5/2024 Final action:
Title: PUBLIC WORKS - Public Works Director Jim Simon
Attachments: 1. CCO-1.pdf, 2. CCO-4.pdf, 3. CCO-6.pdf, 4. CCO-8.pdf, 5. CCO-10.pdf, 6. CCO-17.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
PUBLIC WORKS - Public Works Director Jim Simon
end

Requested Action(s)
recommendation
a) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 1 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform monthly water quality testing, in an amount equal to $7,590

b) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 4 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform potholing, in an amount equal to $15,000

c) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 6 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform potholing, in an amount equal to $11,778.01

d) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 8 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to remove existing concrete foundations, in an amount equal to $5,000

e) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 10 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to maintain existing irrigation systems, in an amount equal to $10,000

f) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 17 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to replace sanitary sewer manhole cone section, in an amount equal to $5,000
body

Financial Impact:
The total financial impact of CCO No. 1, CCO No. 4, CCO No. 6, CCO No. 8, CCO No. 10 and CCO No. 17 is $54,368.01. The Construction (CON) phase of this project is funded by a combination of Federal and State funds comprised of CMAQ, DEMO, SHOPP, ST...

Click here for full text