a) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 1 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform monthly water quality testing, in an amount equal to $7,590

b) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 4 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform potholing, in an amount equal to $15,000

c) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 6 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to perform potholing, in an amount equal to $11,778.01

d) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 8 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to remove existing concrete foundations, in an amount equal to $5,000

e) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 10 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to maintain existing irrigation systems, in an amount equal to $10,000

f) CHANGE ORDER - Request approval and authorization for the Director to issue Change Order No. 17 to the Agreement with S.T. Rhoads Inc. (Road Agreement #2024-03) for the 99W & South Main Street Project, to replace sanitary sewer manhole cone section, in an amount equal to $5,000
body

Financial Impact:
The total financial impact of CCO No. 1, CCO No. 4, CCO No. 6, CCO No. 8, CCO No. 10 and CCO No. 17 is $54,368.01. The Construction (CON) phase of this project is funded by a combination of Federal and State funds comprised of CMAQ, DEMO, SHOPP, ST...